Project Trebel in Brussel

In 2015 and addition in 2016, Staalmeesters rolled curved Bandrasters 100x20x2 mm from Aluminum Extrusion Profile for the Trebel project in Brussels for approximately 42,000 m2 of ceiling area.

The Trebel project involved the demolition of the building on the corner of Trier Street and Belliard Street.  The building consists of three underground levels and eight above-ground floors.  After the demolition with the maintenance of the existing silty wall foundation slab, 3 new underground levels were constructed forming a general pedestal and on top of which two connected buildings 9 and 13 above ground levels were erected.